On August 20th, the Yubileynaya mine hosted an extended technical session with the representatives from the Kuzbassgiproshakht project institute. As part of the meeting the participants examined the surface objects, and, besides, discussed a number of issues related to water treatment plants, mine heating, opportunities for cutting the mine seams, the necessity to upgrade or reconstruct of the main ventilation fan. There was reviewed the schedule for mining stocks with the volume of production, which will be provided in the project.

In the course of the ongoing work this week we have finished casing the degasification well with metal pipes and started concreting the annular space. Besides the United Machinery Technology factory has defined all kinds of work needed to repair the mechanized support units. These activities are reflected in the minutes of the joint meeting, which will be a guide for the factories in charge.