Mine update project

On 24th July we completed the installation of equipment in accordance with the layout as per the manual for dismantling mechanized support units. From July 27th to the surface will be brought the first dismantled support unit, which will later be transported to the factory for repair. After repair the units will be set in the assembly chamber of the extraction pillar 16-17.

Also this week, a coal pump was installed and put into operation in the main drainage sump of the seam 16. Pumping the water inflow of the seam 16 is organized on a regular basis.