Yubileynaya mine project update
In the course of implementing the project on the mine upgrade and the working face preparation the following steps have been made:
1. Slope conveyor 2L-1200 assembled and put into operation
2. Boundary belt incline driven.
The next thing scheduled to be done is assembling a belt conveyor intended for transportation of ROM coal from faces, that will be drifted for delineation of the 16-17 longwall column. The longwall work is set to start in early 2016.